A weekend’s digging on Gower

13th to 14th July 2019

Saturday: Walked the dog, then sorted kit and loaded van, coffee, breakfast and, eventually, on the road to Gower c.08:15. I had left at 08:00 but forgot something and turned back. Arrived at Overton just after 10:30, bit of traffic congestion in Parkmill, got stuck behind a coach. John was waiting.


Looking down the slade.

We chatted while I got my kit sorted then, laden, a stroll along the coast path to the slade and Harry Thomas Cave. At the cave got changed and went underground to take a quick look at the recent progress and to assess what needed to be done to construct the next platform, the main project for this weekend. It was obvious that there was plenty of clearing to be done before any construction work could be started. I returned to the surface, set-up the haul line and pulled the loaded bucket up from the depths, John stayed below and loaded the bucket with bags and stones. There were some breaks while John broke-up some larger rocks, I took the opportunity to take the bags along the path and empty them onto the “scree” slope, I also managed to clear the last of the bags that had previously been dumped along the path. I returned to the cave entrance to haul more bags and stones, then, Danny McCarroll turned up to lend a hand.

When the bags and rocks were cleared from the proposed platform area I went back underground with Danny and together we got to work constructing the platform. Some new ‘acrow bars’ had been purchased and one of these was bolted into place, after a little bit of rock engineering. A second acrow was fixed and scaffold bars attached to make a firm base. Scaffold boards were cut to size to form the platform. Time had passed quickly, it was 17:00 and we decided to call it a day, the last few boards would wait until tomorrow. We packed up and departed the cave.

John and I went to the Ship Inn, Port Eynon for a beer, Danny had to get away so couldn’t join us. After a couple of beers, a fish and chip supper for me, then up to Cefn Bryn to park up for a night’s “vamping”. A chance to try out the extra layer of ‘karrimat’ inserted into the van. Time to write up the day’s events too. It had brightened up a bit but was still a bit chilly, breezy as well.

Sunday: I enjoy these peaceful “vamping” weekends. a decent night’s rest and awoke to a pleasant morning. Coffee brewed, an omelette for breakfast, reading Aldhouse-Green, et. al. 2000. Paviland Cave report and writing in the diary. I had arranged to meet John at c.09:30, after a brief stop in Port Eynon drove to Overton.

Today at Harry Thomas Cave, the platform was completed, boards cut to size and secured, the ladders re-jigged and the job was “a good-un”. We then had another hauling session, clearing bags and rocks from the current end chamber. Initially, the bags were carried up the short ladder and stacked on the newly completed platform before I went up to the surface to haul them out of the cave, john loaded the bucket. It was warm and sunny on the surface.

John then suggested I might lift the “horse” skull recently found to one side of the end chamber, so we returned underground. In the chamber I cleared some loose stones from around the skull and to make access a little easier – it didn’t look like a horse skull to me – took some photographs, also noted another dog skull and other remains. The skull was in fair condition and almost complete, it was easy to lift – it was obviously a sheep, John wasn’t so interested with it after that.


The skull.

By now it was time to start packing things away and exit the cave, there was some discussion regarding various aspects of the end chamber. I picked up my drill bag on the way out of the cave. The cave secured, we departed. A brief chat at Overton before parting company.


A visitor to the cave.

I was heading along the heads of the Valleys road (A465) to the Lamb and Fox, Pwll Ddu to a wake for Brian Lewis, the former landlord. 25 years ago, during the heady days of discovery in Ogof Draenen, Brian and Carol had been very good to us. Met up with several old friends and raised a glass to Brian.

Wookey Hole, Mendip

27th December 2018: with Roz, Brockers, Nick, Tav and Jon.

Had purchased some supplies and a good team assembled to help carry the equipment, including drill bag, sundries bag, drill-bit tube, wire and a 3.5m aluminium ladder, into the cave. There was some debate regarding the length of the ladder, so Brockers carried in a hacksaw, just in case. A careful trip through Chamber 20 to the sand dig where there was plenty of evidence for recent slumping.

With a bit of jiggling the ladder was installed and I was able to drill 4no. holes into the slab of rock. Brockers passing various bits of kit and stuff as and when required. The rest of the team spent time sorting out the spoil heap and ran-out the wire. The holes were charged, and the evening brought to a satisfactory conclusion from a safe location.

Hunter’s!

Sandy Bay/Middle Hope, North Somerset

23rd December: Spur and furrow morphology at Sandy Bay, North Somerset.



The spurs comprise silts and clay with some sand, the base of the furrows being lined by a coarse pebble/fine cobble layer, which could be an underlying sediment or a lag deposit dragged into the furrows by the tide.

Swallow Cliff Bay drift sequence. The most complete exposure is found in the south-eastern corner of the bay (right-side of image) where it rests on the fossil shore platform, here it is cut into [Carboniferous] basaltic lava at about 12.5 m OD.



Reference: Case, D.J. 2013. The Coast of the Bristol Region: Quaternary Geology and Geomorphology. Geologists’ Association Guide No. 71

Wookey Hole, Mendip

6th December 2018: With Duncan, Jonathon, Nick, Tav and Alex

The trip through Chamber 20 didn’t appear to be much wetter than last week, in spite of the recent rain. At the sand dig, the water level had risen c.150-200mm and was encroaching into the alcove. Everything at the bottom of the dig was slippery, the self-digging hadn’t occurred, and the large, precarious slab of rack was still overhead. After some protracted discussion, it was decided that the rock needs to be dealt with before digging can continue [relatively] safely, some chemical persuasion is required, it will be done!

Tav suggested that we might re-locate the retaining wall and so create extra spoil dumping space, this seemed a good idea so, that’s what we did for the evening.

I had a less than comfortable trip out of the cave, the sole of my boot had decided to become detached and go solo, one moccasin is not great for caving – or one socked foot either!

Wookey Hole, Mendip

29th November 2018: Last weeks digging session was abandoned for the pub when only three of us turned up at Wookey Hole.

Better turn-out this week, with Nick, Tav, Jonathon, Duncan, Mike and, course yours truly, all keen and raring to go, unfortunately Roz got left behind and wasn’t happy about it!

After some persistent wet weather recently, we weren’t all that hopeful about this evening’s prospects but, we headed off anyway. The cave was active, the sound and sight of dripping, running water all the way up through Chamber 20. At the sand dig, the anticipated puddle of water but, rather surprisingly, not as deep as expected.


The excavation had become self-digging as more had slumped from the roof to reveal a space overhead, which was encouraging, and potential lead(s). Some digging was possible but continual slumping and a large, suspect slab overhead soon put an end to it. That was, until Nick decided to poke a bar into the bottom of a small pool of water that became a flow of water and a pile of sloppy sediment. After some more interventions, more slumps, and time running-out, we decided to leave it to settle down, perhaps continue to self-digging and return next week. hopefully, the water will continue to drain freely, and wet conditions will not impede further progress too much.

To the pub!

Wookey Hole, Mendip

15th November 2018: with Jonathon, Mike, Nick and Alex

Surprisingly, the sand dig was dry and didn’t appear to have backed-up at all after the very heavy rain last weekend. However. A seepage of water through the sediments in the alcove had caused some slumping and work was concentrated there to tidy-up and consolidate. The trickle of water that enters from the chamber was constant, making the steps slippery so these were tidied up too, very sloppy spoil. The water from the trickle is draining freely through the sandy sediment at the bottom of the dig.

Alex and Nick shared the digging, Mike loaded the filled buckets into the skip, Jon hauled the skip up the slope and I emptied the buckets. The process was, of course, repeated many times.

Wookey Hole, Mendip

8th November 2018: with Alex, Mike, Jonathon and Roz

It’s been raining recently and all the way up through Chamber 20 the results of this were clear; the drips were stronger, pools were filling-up and water was flowing down the calcite cascade. However, on arrival at the sand dig, we were pleasantly surprised to find it bone dry and no signs of water having flowed into it, this despite the small tube being full and overflowing.

Alex climbed down into the pit and began digging in the alcove, I was moving the filled buckets and passing them up to Mike, who then placed the filled buckets into the skip, hauled by Jonathon, Roz was in control of spoil dispersal. The empty buckets were returned, the process repeated, many times.


Alex reaches for the mattock

In between moving buckets, I spent a little bit of time tidying-up a section of the sediment bank where evidence of flooding and subsequent draining events is clear. It really needs more time spent on it and a full section cleaned and recorded.


Height of sediment sequence c.100mm

All too soon it was time to move the tools to higher ground, just in case, and depart the cave.